Electrostatic Precipitator Condition Inspection

Client: MSF Sugar
Completed: 2024
Subject Matter Experts + Construction Advisory Management and Supervision

Scope

MSF Sugar requested an Electrostatic Precipitator (ESP) material redesign due to suspicions of severe internal corrosion.

Challenges

  • Client initially proposed unproven material for retrofit.
  • Relatively new plant with limited funds budgeted for a redesign/rebuild of the ESP.
  • Process operating conditions were not achieved with limited OEM Engineering information available.
  • ESP had been exposed to a plant fire leaving the internal material integrity largely unknown.

Outcomes

  • Client avoided an unnecessary multi-million-dollar retrofit.
  • Issue was downgraded from an immediate structural risk to a manageable maintenance/upgrade task.
  • Operating team received clear justification for the chosen approach.
  • Internal stakeholders had a common, defensible position to present to the board.